Source: http://help.sap.com/saphelp_scm50/helpdata/en/05/f8923945b12c4de10000000a114084/frameset.htm
During scheduling based on SNP master data, the system determines durations as follows:
· The unloading time (duration between unloading date and delivery date/time) corresponds to the goods receipt processing time, which is defined on the GR/GI tab page in the product master data that is dependent on the destination location.
· The transportation time (duration between delivery date/time and goods issue date) is the time defined in the transportation lane.
· The loading time (duration between goods issue date and material availability date) corresponds to the goods issue processing time that is stored on the GR/GI tab page in the product master data that is dependent on the start location.
· The pick/pack time (duration between material availability date and loading date) corresponds to the pick/pack time for VMI that is stored on the GR/GI tab page in the product master data that is dependent on the start location.
· The transportation planning time (duration between loading date and transportation planning date) corresponds to the transportation planning time for VMI that is stored on the GR/GI tab page in the product master data that is dependent on the start location.
Durations for Scheduling Based on SNP Master Data